Nov 2024 – March 2025 – Preliminary & Enabling Works. This includes site preparation, fencing, vegetation management, protection measures, and access tracks.
April 2025 – Sept 2025 – Primary Construction, including solar development and substation works.
Oct 2025 – Jan 2026 – Testing and Commissioning, as well as landscape implementation.