Nov 2024 – March 2025 – Preliminary & Enabling Works. This includes site preparation, fencing, vegetation management, protection measures, and access tracks.
August 2025 – June 2026 – Primary Construction, including solar development and substation works.
June 2026 – September 2026 – Testing and Commissioning, as well as landscape implementation.